|
|
PVC Installation Procedures
Back to Installation Guides
SECTION I: GENERAL SEQUENCE
OF EVENTS
Back to Table of Contents
- See attached "Check-Off List of Materials" and prepare materials
necessary for lining installation.
- Only unfold the panels that are to be anchored or seamed together
in one day. See section VI, "Unfolding and Spreading Prefabricated Panels".
- After the panels are initially placed, remove as many wrinkles as
practical. If possible, allow the panels to "relax" by warming in
the sun. The edges to be bonded should be as smooth and free of wrinkles
as attainable
to ensure smooth and wrinkle-free field seams.
- When panels are in position, commence field seaming operations.
See section VIII "Recommended Guidelines for field seaming procedures using
solvent Adhesive".
- At the end of each day all unseamed edges should be anchored by sandbags.
If winds are expected, boards along the edges of the panels, with sandbags
on top, should be used to anchor liner, or a "wind row" of backfill material
placed three-feet back from leading edge. Other ballast materials,
such as rolls of geotextile may be used at the determination of the installer.
- After field seaming is completed in a given area, and ONLY then should
liner edges in the anchor trench should be buried.
NOTE: Do not bury the liner edge in the anchor trench
within 30 feet of an incomplete" field seam. This is to allow
the seam area to be re-tensioned to remove wrinkles along the seam area.
- To begin the field seaming, always start in the middle and work toward
an open end. This will minimize large wrinkles from becoming
trapped - which will require cutting and patching.
- An earthen cover should be placed over the lining in one lift.
SECTION II: INSTALLER FURNISHED MATERIALS
FOR INSTALLATION
Back to Table of Contents
Installer should supply the listed materials for installation of prefabricated
panels of AccuGeo Liner PVC Liners
- All field installation labor and official supervision, i.e., crew
chief or foreman.
- The means to move packaged, folded panels of liner to specific locations
on site. Panels will weigh up to 6,000 pounds.
- Stakes and string or chalk lines (not lime) to define panel location
and initial unfolding guidelines.
- Canvas, burlap or polyethylene bags filled with sand, or soft dirt,
to hold the unseamed edges in place. Quantity depends on wind
present during installation; figure one (1) bag per ten (10) feet
of unanchored panel perimeter. Note that continuous ballast must
be provided along an unsecured edge for strong wind conditions.
- Minimum of (2) hand rakes, or large paving rakes and (2) shovels.
- One or more compacting rollers for smoothing out or compacting rough
or badly gouged earth at the pit site.
- Portable hot air gun, extension cords, and power source (See "Tool
List For Field Seaming Crews").
- Box or barrel of clean cotton rags.
- Surveyor's tape measure.
- Can of surveyor's spray paint.
- All proper safety equipment and supplies. The customer is
responsible for all safety aspects of the installation.
- All persons at the site should have smooth, protrusion-free shoe
soles (no heels) tennis shoes or smooth, rubber-soled work shoes.
- If field seaming will be performed, all required equipment listed
on the attached "Tool List for Field Seaming Crews" should be provided.
- All workmen should wear gloves so the hot liner will not blister
the back of their knuckles while spreading the panels. This is particularly
true during the summer months.
- Each crew member should have a 1' x 2' grade stake (with pointed
end cut off) or dowel. These will be used to prevent damage to the
panel when spreading and to protect the crew members hands. The folded
edge of the panel should be rolled around the stake in preparation for
spreading the panel.
SECTION III: INSTALLER MAKE-READY LIST
Back to Table of Contents
Preparations to be made the afternoon or evening before commencement
of the lining operations.
________________________________________________________________________
- All equipment, tools and supplies to be at the pond site and properly
stored.
- Soil sterilant should be applied when control of vegetation is needed.
- The first day's panels to be in position. Leave the panels
packaged. If hot sunlight is present, shade the panels using any
opaque sheeting. Leave a free-flowing air space between the opaque
sheeting and the panels.
- An anchor trench dug, if required, entirely around pond. The
soil should be spread out (raked back, flat, away from anchor trench) so
panels can be unfolded on the top of the berm.
- Stakes installed and/or lines measured and drawn indicating panel
locations, reference lines, etc...
- All pond dimensions checked to verify actual pond dimension are not
greater than shown on the drawing.
- Pond preparations for the covering of the liner:
A. Pond surface raked smooth, rolled if necessary. Free
of all large, sharp rocks, or other sharp objects, and free of all vegetation
and/or stubble. Soil sterilization shall be performed if required.
B. All penetrations, (pipes, etc.) covered or wrapped to protect
liner from being cut, abraded or punctured during installation.
C. Where bonding of liner to concrete is required, the surface
should be smooth, clean, dry and smooth finished.
D. All pipes, drains, fitting, etc., which are to be installed
beneath the liner, should be in place and ready to be covered with the
liner.
- Distribute sandbags (about one every ten feet) along the perimeters
of the area to be lined the next day. DO NOT put them in the area
where the panels will be unfolded, but immediately adjacent.
SECTION IV: FABRICATOR PACKAGING
Back to Table of Contents
The PVC lining is accordion folded (in both directions) to fit on the
pallet. Liner panels are wrapped with a protective cover of sacrificial
.010" PVC liner and adequately packed and loaded for shipment to prevent
damage during transit. Wooden pallets shall be free from mechanical
obstructions such as nails, screws, or other fasteners etc. that may damage
lining .
Any lining that is damaged during shipment, storage, or installation
must be repaired by the Contractor before placement of the protective cover
materials or backfill.
SECTION V: CONTRACTOR STORAGE
Back to Table of Contents
The PVC lining material should be stored at the job site in it's original
unopened packaging to protect the material against damage. When possible,
PVC liner material should be stored in dry areas offering protection from
direct heat of the sun especially if the storage period is long.
Space should be allowed between each liner pallet for ease of identification
and abrasion prevention. Pallets of liner shall never be stacked.
SECTION VI: UNFOLDING AND SPREADING PREFABRICATED
PANELS
Back to Table of Contents
- The Liner panel is marked on the outside covering indicating the
panel identification letter or number. (The panel markings are also
on the material inside the packaging).
- When ready to unfold the panels, remove the packaging carefully.
DO NOT USE A KNIFE AS DAMAGE TO LINER MAY OCCUR. Before unfolding
panels from the pallet, carefully inspect for protrusions and remove any
protrusions which may cause damage.
- Positioning the panel and unfolding it from the pallet is best handled
with a large four-yard front-end loader or forklift. The panel
may weigh as much as 6000 pounds.
- After the panel is unfolded, it is straightened out to the layout
guidelines.
- The panel is then spread into position. Men are positioned
at the edge of the panel as indicated by the Crew Chief. The men
are positioned approximately 15 feet apart, depending on the size of the
panel and the terrain to be covered. If required, men are positioned
at the uphill end of the panel to keep it from sliding down the slope as
it is unfolded. If the edge to be gripped is subsequently to be bonded,
then the panel edge is folded back about two(2) or three (3) feet creating
a fold. The fold is gripped using the 1' X 2" grade stake or dowel
wrapped in the material for pulling inside the panel rather than the edge
itself. This is to avoid stretching the edge where it is to be bonded.
- As the panel is pulled out it is necessary to maintain air under
the liner for buoyancy. This can be accomplished in several ways.
One is to simply hold the edge and advance at a rate fast enough to create
air under the liner as it is unfolded. Another is to "fan" air under
the liner. This is done by raising and lowering the edge of the panel
to create a wave like action across the liner as it is being spread.
This fanning action should be directed by the Technical Service Representative
or Crew Chief.
Caution should be observed when spreading the panel under windy conditions.
The panel should always be pulled into the wind to facilitate proper air
flotation. Extreme care must be taken to prevent the liner from getting
out of control and blowing away.
- A slight lateral tension on the leading edge of the panel being spread
should be maintained. This lateral tension facilitate the spreading
operations.
________________________________________________________________________
NOTES:
- During unfolding-spreading operations it is necessary that the crew
wear gloves, as these operations can be quite chafing to the knuckles.
- During unfolding-spreading operations it is necessary that the crew
work as a team.
- If a gust of wind begins to pull the liner away from the crew and
they are about to lose their footing, the following points are applicable:
1. Apply lateral tension in the leading edge and lower it to the
ground.
2. Attempt to restrain it further by placing one knee on the leading
edge.
If these efforts fail to restrain it, LET IT GO, DO NOT HOLD ONTO THE
LINER, DON'T BE PULLED ALONG WITH THE WIND.
- Extreme caution should be exercised when walking on the PVC liner
material when wet. The sheeting becomes very slippery. It is
often necessary to use a rope as an aid in going in or out of ponds.
SECTION VII: RECOMMENDED GUIDELINES FOR FIELD
SEAMING PROCEDURES USING SOLVENT ADHESIVE
Back to Table of Contents
Seaming
- Temperatures for seaming must be as follows:
Minimum ambient temperature:50 degrees f.; Minimum liner temperature:
90-100 degrees f.; Minimum solvent adhesive temperature: 70-80 degrees
f.
- Before adhesive is applied, surfaces to be seamed must be free of
dirt and foreign materials. The presence of a few particles of sand
or dirt is permissible in situations where it is unavoidable. The
acceptable limit is when the particles are totally encapsulated in the
adhesive/seam and they do not connect to form a path for a leak.
- Adhesion of one liner panel to another is accomplished by lapping
the edges of panels a minimum of 3-inches (6-inches is more desirable).
The contact surfaces of the panels should be wiped clean to remove all
dirt, dust or other foreign materials. A clean cloth, foxtail or
grout brush may be used. If adverse conditions exist, such as mud,
caked mud, or clay, remove by clean water wash. Then dry before attempting
to continue with seaming procedure. A seaming board should be placed
under the liner portion to be immediately seamed. Adhesive can be
applied by use of squeeze bottles or cans with brushes for the length of
the seaming board. Cans and brushes must be used cautiously with
a lid slit barely large enough to accept the brush, otherwise the adhesive
can lose its "solvent grab" through evaporation of volatiles or contamination.
Always keep the dispensing vessel sealed when not in immediate use.
The actual bonded area must be continuous, extend to the exposed edge of
the seam be a nominal 2"-3" wide and have a minimum width of 1/2 inch.
Using too much PVC bonding solvent in a wide area could result in a poor
quality seam. With a typical 2 inch wood or plastic wallpaper seam
roller, burnish the freshly joined areas by rolling perpendicular to the
seam squeezing out excess adhesive and air pockets.
- "Fishmouths" can be folded over and bonded closed or slit, bonded
down and patched per instructions given by the Technical Advisor.
Patches over "fishmouths" or other seam flaws should extend at least 2
inches past the flaw in question. The rule on patching should be:
"If there is questions as to whether or not to patch, then patch it"!
Repairs
Before making repairs, the contact surfaces of the lining shall be thoroughly
cleaned to remove all dirt, dust, moisture, and other foreign materials.
When making repairs, a hot-air gun or other approved heating device shall
be used to warm the lining when the ambient air temperature is below 50
F. No lining repairs shall be made when the ambient air temperature
is below 35 F. A solvent adhesive supplied or approved by AccuLiner,
Inc. shall be used in the repair work. All lining repairs shall be
made using patches of parent material with rounded corners. Any area
repaired shall be inspected and approved by the Contracting Officer before
placement of any cover.
SECTION VIII: PATCHING INSTRUCTIONS FOR PVC
LINERS
Back to Table of Contents
Patches must be made from the parent material (same gauge or thicker
PVC) and be cut to allow a minimum of 3" overlap outside of the damaged
area for bonding. The patch is to be applied with the same adhesive
as used for liner seaming and must be rolled and/or burnished to ensure
a complete seal.
SECTION IX: FIELD SEAM TESTING METHODS FOR
SOLVENT ADHESIVE WELDS
Back to Table of Contents
All field seams made to join liner panels or penetration details (such
as pipe boots) shall be 100% both visually inspected for integrity or air
lance tested using a pressure of 40 p.s.i.. Any areas found not to
be properly bonded shall be identified by Q/C Inspection personnel for
patching or other appropriate measures to correct the condition.
Any problematical areas found shall be visibly identified with a bright
marker that will not interfere with repair process itself. After
repairs are made, every identified area must be re-inspected and approved
by Q/C personnel before backfilling operations over the affected area are
to occur.
Optional (existing job specifications may overrule)
Non-destructive coupon samples shall be taken at least twice each day
for each seaming technician at the beginning and end of field seaming operations.
Non-destructive coupon samples shall have minimum measurements of 12" X
24" (lengthwise being parallel to the seam direction) and shall be identified
as to the time of day, adhesive used and the name of the seaming technician.
Coupon seams shall be cured for a minimum of 20 hours including at least
6 hours of direct sunlight exposure and the balance being at room temperature.
Testing shall be in the shear and peel directions. Test methods and
passing criteria shall be in accordance with NSF 54-1991. The Installation
Contractor shall draft an as built drawing of the liner system concurrently
with the progression of work to be retained as a permanent record of the
job. This drawing shall include the identification and location of
all installed panels.
SECTION X: RECOMMENDED GUIDELINES FOR FIELD
SEAMING PROCEDURES USING WEDGE WELDERS
Back to Table of Contents
This guideline recommends that wedge welding and related Q/C procedures
be decided upon by the installation contractor. Any such intention
should be with the knowledge and approval of the concerned Project Engineer
and/or Owner.
SECTION XI: INSTALLING PIPE BOOT PENETRATION
DETAILS
Back to Table of Contents
Whenever possible, avoid slitting liner panels for piping details until
boot itself is ready for immediate installation. Generally, it is
best to let the lining material straddle a relatively small protrusion
(for later detail work) provided that the object is first blunted (i.e.
attached rag etc.) to avoid abrasion or other damage to the liner.
Premature cutting of a liner panel for a penetration detail can lead to
serious damage to the liner in situations where winds and/or precipitation
may occur and the liner is not well ballasted or otherwise protected.
Cuts made in liner for clearance over protrusions should always be made
as small as possible to minimize possible patch work or wind damage etc.
Factory prepared pipe boots should fit snugly but not require excessive
force to pull over a detail. If a boot feels overly snug but workable,
try applying either talc powder or using compressed air with a nozzle to
float the boot sleeve over the pipe. Boots should never be installed
that require enough force to permanently stress or weaken them. When
properly installed, the pipe boot will lay flat against grade surrounding
pipe without leaving pockets that may become stressed both during and after
placement of backfill. Pipe boot aprons shall be seamed to the parent
liner at the interface surface using the same techniques as described in
section VII. In any instance where an apron doesn't cover a open area,
that area shall be patched in accordance to repair procedures mentioned
in section "VII repairs". Proper leakproof sealing of boot details shall
be verified by air lance or pick technique yielding no lose or curled edges.
The pipe boot sleeve shall be attached to the pipe using the clamping/sealing
detail specified in job drawings or by engineer.
SECTION XII: TOOL LIST FOR FIELD SEAMING
CREWS
Back to Table of Contents
- One (1) set size 10 cloth gloves.
- Two (2) set knee pads. (If desired)
- Roll of tape to hold on knee pads.
- Ten (10) cotton rags per hour (24# box normally is adequate).
- Gallon can with handle for adhesive. Plastic applicator bottles
can be ordered from AccuLiner, Inc.
- One (1) whisk broom (or fox tail brush).
- One (1) 1" X 10" X 1'4-16' long Douglas fir clear board, rounded
off on both ends as well as all edges, with a rope tied to one end to be
used as a seaming board.
- One (1) Stanley Knife.
- One (1) red or yellow crayon for marking liner surface.
- One (1) pair of scissors with rounded-off points.
- Safety glasses for each man on seaming crew for protection from
solvent splash.
- One (1) 2" plastic or wood wallpaper seam roller per each field
seaming crew.
SECTION XIII: COVERING PVC LINER
Back to Table of Contents
- Care must be taken by equipment operators to avoid damaging the PVC
liner.
- Heavy equipment should operate on a minimum 3 foot roadway where
the "haul road" is established in and out of the pond.
- Always operate equipment on a minimum of 12 inches of covering.
Avoid sharp turns with equipment that could pinch and rupture the liner.
- When covering the side slopes always push cover material up the slope
from the bottom of the pond. This will avoid stressing the liner.
- If damaged does occur, DO NOT COVER IT UP. Advise the foreman
so repair can be made.
SECTION XIV: MISCELLANEOUS ATTACHMENTS
Back to Table of Contents
|